Page 19 - BIM and ISO 19650 from a project management perspective
P. 19

The process of delivery, according to ISO 19650 Part 2, Section 4.1 Information management process, is detailed in the figure below.





















                          KEY
                          1   assessment and need                          A   information model progressed by subsequent delivery team(s) for each appointment
                          2   invitation to tender                         B   activities undertaken per project
                          3   tender response                              C   activities undertaken per appointment
                          4   appointment                                  D   activities undertaken during the procurement stage (of each appointment)
                          5   mobilization                                 E   activities undertaken during the information planning stage (of each appointment)
                          6   collaborative production of information      F    activities undertaken during the information production stage (of each appointment)
                          7   information model delivery
                          8   project close-out (end of delivery phase)

                          Figure 5: Information delivery process with Stages 1-8, according to ISO19650 - Part 2




                          Two aspects should be noted:
                                  • the starting point is the specification of requirements, Stage 1: Assessment and need

                                  • the final point is project handover, Stage 8: Project close-out

                          Consulting engineers are affected at an early stage, Stage 3: Tender response.



                                                                                                                                                                 19
   14   15   16   17   18   19   20   21   22   23   24